Sunday, November 22, 2009

Couple of things b4 our Contract Appointment

We are nearing our contract appointment.
We gotta do couple of things b4 our appointment.

  • We need to apply for dispensation to council coz, our garage offset from side boundary is 900mm instead of 1m. We did that. Waiting for their approval.
  • We were noted that on tender appointment our Tender Presentor advised that meter box would go on left left hand side (garage side wall) instead right jhand side( usual business side) When we contacted Energy safe Victoria, we were clarified that 1m of clearance is essential from the face of meter box (we are 100mm short) so we contact H3nl3y and advised them to change that to other side which gonna cost us $300 for additional cabling for 10metres.
  • We changed our carpet color from TAIL GATE to EMINENCE, SDN carpet.

All done...Eagerly waiting for our contract documents and drawings to go...